Two Odisha REAT rulings reported in the first week of November 2026 matter to anyone who has bought, owns or manages a flat in a project that was delivered late or built differently from its sanctioned plan. The Odisha Real Estate Appellate Tribunal (REAT) hears appeals from the Odisha Real Estate Regulatory Authority (ORERA). In one case it confirmed how much interest a delayed buyer is owed and corrected the rate ORERA had used. In the other it upheld a heavy penalty on a developer but held that ORERA has no power to order a development authority to demolish a building.

Ruling 1: Royal Habitat – delayed-possession interest at the Rule 16 rate

In S.J. Developers & Housing Pvt. Ltd. v. Secretary, ORERA (project "Royal Habitat", Govindpur, Jatani Road, Khordha), the promoter appealed an ORERA order of 20 May 2023 in Complaint Case No. 204 of 2021 that had awarded a buyer interest for delayed possession under Section 18(1) of the RERA Act. By an order dated 12 October 2026, REAT dismissed the appeal. It rejected Cyclone Fani and Covid-19 as force majeure excuses and noted that the tower in question was completed in August 2023 without an occupancy certificate.

The tribunal then changed the arithmetic. ORERA had used 9.70 per cent. REAT applied Rule 16 of the Odisha Real Estate (Regulation and Development) Rules, 2017, which pegs the rate to the State Bank of India MCLR plus two per cent, working out to 10.45 per cent from 17 August 2019 and 10.25 per cent from 1 November 2019, according to the IBC Laws report of the order. Any balance after adjusting the statutory deposit is payable within 45 days. [UNVERIFIED – confirm the rates, dates and 45-day direction against the order PDF before publishing.]

Ruling 2: Puri – ₹90 lakh penalty stands, demolition direction does not

In a separate matter reported on 5 November 2026, REAT upheld a penalty of about ₹90 lakh that ORERA had imposed on the developer of a project at Sipasarubali, Puri. The complaint, filed in 2024, said a G+10 commercial-cum-residential building had been raised where a G+7 residential project was approved. ORERA found that the revised plan lacked final approval from the Puri-Konark Development Authority (PKDA) and that mandatory clearances were missing. The project cost was put at about ₹166 crore, so the penalty is a little over half a per cent of it. [UNVERIFIED – developer name, order date and the RERA section under which the penalty was imposed are not given in the available report.]

ORERA had gone further and directed PKDA to demolish the unauthorised portions. REAT set that part aside: the regulator's powers under the RERA Act do not extend to directing a development authority to demolish. Any demolition has to be pursued separately under the Odisha Development Authorities Act. The report adds that PKDA had in the meantime regularised the G+10 structure on payment of compounding fees by an order dated 21 May, and that REAT, citing Supreme Court guidance against regularising illegal construction, left the validity of that regularisation open. [UNVERIFIED – year of the PKDA order not stated.]

Why the two Odisha REAT rulings matter together

Read side by side, the rulings draw a clear line. ORERA is the forum for money remedies – interest, refund, penalty – and REAT will hold it to the rate the Rules prescribe. Structural remedies against a deviating building belong to the development authority (BDA, PKDA, CDA) under the ODA Act, which is the same statute behind the BMC and BDA action on commercial use of residential buildings in Bhubaneswar.

Description

What this means for owners

If you bought a flat that was handed over late, the interest you can claim before ORERA is not a matter of negotiation; it follows Rule 16. Keep your agreement, payment receipts and the promised possession date together. If your building deviates from its sanctioned plan, a RERA complaint can get you compensation and a penalty on the promoter, but it will not by itself get the deviation removed or regularised – that question sits with the development authority, and a regularisation order is not beyond challenge. Owners who live outside Odisha should check whether their project ever received an occupancy certificate, because its absence featured in both cases.

What this means for tenants

Tenants are not parties to these disputes, but they feel the consequences. A building without an occupancy certificate, or with floors built beyond the sanction, can face notices, utility disconnection or sealing by the development authority regardless of what ORERA has ordered. Before signing, ask to see the occupancy certificate and the sanctioned plan, and make sure the lease says what happens to your deposit if the premises are sealed.

What Navoasset does

For every property we take on, we collect the sanctioned plan, occupancy certificate and RERA registration before the first tenant moves in, and we flag deviations to the owner in writing. For owners with a delayed-possession or deviation grievance, we compile the document set an ORERA complaint needs and coordinate with the owner's advocate. For away and NRI owners, we attend development-authority hearings in person so a notice never goes unanswered.


Sources & documents

  • IBC Laws, "Odisha REAT Upholds Delayed Possession Interest, Revises Rate Under RERA Rules", 2 Nov 2026 – citation (2026) ibclaw.in 706 REAT; order dated 12 Oct 2026; CC No. 204/2021; ORERA order 20 May 2023; rates 10.45% / 10.25%; 45 days. https://ibclaw.in/odisha-reat-upholds-delayed-possession-interest-revises-rate-under-rera-rules/
  • PropNewsTime, "Odisha REAT upholds INR 90 lakh penalty on Puri developer, sets aside demolition order", 5 Nov 2026 – Sipasarubali, G+10 vs G+7, ₹166 Cr cost, PKDA regularisation order dated 21 May, Sections 35–38 context. link
  • Context only: IBC Laws, 14 Oct 2026 – REAT sets aside ORERA ₹12 lakh penalty (Sriram Vihar, Cuttack) for breach of natural justice, order 30 Sep 2026, (2026) ibclaw.in 640 REAT. link
  • Odisha Real Estate (Regulation and Development) Rules, 2017 – Rule 16 text to be downloaded from rera.odisha.gov.in (the announcements page rendered empty for an automated fetch; open it in a browser).