A second Odisha semiconductor plant has been approved. On 15 September 2026, the Unit Approval Committee of the Falta Special Economic Zone cleared a Rs 3,406.25 crore proposal from SiCSem Private Limited to make silicon carbide (SiC) chips at IDCO Infovalley-II in Khordha district [1][2].
Silicon carbide chips are power electronics. They are used in electric vehicles, EV chargers, solar inverters and rail traction.
The three projects in the Jatni–Khordha cluster
ProjectInvestmentStageKey numbersSiCSem unit 1, Info ValleyAbout Rs 2,066.70 crore [3]Under construction since November 2025; India Semiconductor Mission support agreement signed 11 May 2026 [3][4]60,000 SiC wafers a year processed; 96 million units packaged a year; about 5,000 direct and indirect jobs; target start 2027-28 [4]SiCSem unit 2, Infovalley-IIRs 3,406.25 crore [1]Approved 15 September 2026 [1]21.889 acres at Arisol mouza, Jatni tehsil; 4.8 million SiC diodes and 91.2 million SiC MOSFETs a year [1][2]Intel and 3D Glass Solutions packaging substrate facilityAbout US$3.3 billion [5]MoU signed in May 2026 to explore the project [5][6]Glass-core packaging substrates in the Bhubaneswar–Khurda region, built in phases over 5–6 years [5] SiCSem's first plant is a partnership with the UK's Clas-SiC Wafer Fab, with a research lab at IIT Bhubaneswar [4]. In October 2026, the state Cabinet also amended Odisha's semiconductor policy [7].
The Intel–3DGS agreement is an MoU to explore the project, not a final investment decision. Treat it as a possibility until a site and a construction start are announced.
What the government says it wants
The state's stated aim is to put Odisha on the global semiconductor map, create skilled jobs for local youth and attract other global technology companies [6]. The approvals are aligned with the India Semiconductor Mission's goal of reducing India's dependence on imported chips.
Areas to watch
AreaLink to the clusterWhat to watchArisol mouza, Jatni tehsilThe second SiCSem siteLand use around the 21.889-acre site, and the access roadJatni townThe nearest town to Infovalley-IIRental demand from engineers, technicians and contractorsKhordha town and Khurda RoadRail and road gateway for the beltWorkforce housing and servicesBhubaneswar south-westCommute zone to JatniDemand from senior staff who choose city homes Chip plants employ fewer people than their cost suggests. Their workforce is skilled and well paid, though, which supports good-quality rental housing. Suppliers and service firms also tend to follow an anchor plant into an area.
What owners in Jatni and Khordha can do now
- Get the letting basics right before demand arrives. Our guide to what owners get wrong when letting a flat in Bhubaneswar applies to Jatni and Khordha too.
- Verify every tenant. Incoming project staff and contractors should go through tenant and police verification like any other tenant.
- Know where tenants want to live. Commute time to the workplace drives demand; see where tenants actually want to live in Bhubaneswar.
What happens next
- Construction progress at SiCSem unit 1 against its 2027-28 target
- The groundbreaking date for SiCSem unit 2
- Whether the Intel–3DGS MoU becomes a firm investment with a named site
More from Odisha Development Watch
- Odisha clears Rs 2.47 lakh crore in 27 projects, led by Khordha data centres
- Puri international airport gets final environment clearance
- Bhubaneswar metro rethink and the 645 km ring road plan
Own property in Jatni, Khordha or Bhubaneswar and live elsewhere? See how Navoasset manages property in Bhubaneswar and Odisha, or request a call back.
This article reports public information for general awareness. It is not investment or legal advice.
Sources
- UNI, 15 September 2026: Odisha: Rs 3,406-crore SiCSem semiconductor project approved.
- Swarajya, 16 September 2026: Rs 3,406 crore silicon carbide semiconductor plant approved in Odisha.
- Communications Today: SiCSem to launch first silicon carbide semiconductor fab in Odisha.
- Evertiq, 3 November 2025: SiCSem starts work on $220M chip production plant in India.
- Drishti IAS, 1 June 2026: Odisha partners with Intel and 3DGS for semiconductor facility.
- Government of Odisha, press release, 29 May 2026: Intel and 3D Glass Solutions exploring an advanced semiconductor glass-core packaging substrate facility in Odisha (PDF).
- OdishaBytes, October 2026: Odisha Cabinet approves amendment of semiconductor policy.